What progress was made on your grant this month?
Please summarize your progress in 3-5 sentences or bullet points:
s5_messengerwas brought to initial release state. It now has a published package and a functional example demo app.- Work on the main app, Luogo, has started. Maps integration (through self hosted protomaps) is complete ← video demo.
- Performance work has been done on lib5 which dramatically reduced CPU usage (from 200% to 20%) making it feasible to use on mobile.
Summarize any problems that you ran into this month and how you’ll be solving them.
Please summarize your issues into a few sentences or bullet points:
- No significant issues have been run into this month and work is on pace.
List repos worked on this month with links to PRs and relevant commits:
What will you be working on next?
Please summarize your development goals into a few sentences or bullet points:
- Continue work on the main app, Luogo, to complete features like live location sharing. Get a MVP app completed by the end of July.
- Figure out some basic branding & make a logo.
- Migrate the
s5_messengerpackage tos5version 1.0.0. This likely will begin this month but not be completed until August as the messenger package is functional right now and I want to put most of my cycles into getting the app in a good spot. - Figure out invites with MLS without having to have the other users keypair already.